Hoffman Elementary School

Northside Independent School District

Project Data

Project Description: A new elementary school – kinder through 5th grade, 36 classrooms with 9 pull out classrooms.

Engineer: Silber & Associates

Architect: PBK Architects

Project Architect: Joel Hernandez, AIA

 

Construction Data

Date Started: October 2007

Date Completed: June 2009

Square Footage: 104,660

Student Capacity: 800

Construction Contract Amount: $18,954,000.00

Total Value of Change Orders: TBD

Cost Per Square Foot: $181.01

General Contractor: Bartlett-Cocke General Contractors

Construction Contract Type: CM at Risk


HOFFMAN 2