Brandies High School

Northside Independent School District

Project Data

Project Description: A new high school with 59 classrooms, 16 science classrooms, 9 computer classrooms, auditorium and theater, also provided are facilities for football, baseball, softball, soccer, basketball and tennis.

Engineer: Silber & Associates

Architect: Noonan Rittiman Architects

Project Architect: Craig Noonan, AIA

 

Construction Data

Date Started: March 2006

Date Completed: May 2008

Square Footage: 429,667

Student Capacity: 2,800

Construction Contract Amount: $69,689,851.00

Total Value of Change Orders: <$155,183.00>

Cost Per Square Foot: $162.19

General Contractor: Bartlett-Cocke General Contractors

Construction Contract Type: CM at Risk